Create Internal Budget Transfer - Project Manager
To create an internal budget transfer, complete the following steps:
- Click Edit mode from the Budget page
- Click the three dots next to the budget category that you wish to move money from, and then select Budget Transfer:
- Select the budget category that you wish to move money into.
NOTE: Only budget categories used in your existing budget will be displayed by default. If you are moving money into a new (unused) category, you will need to select "Create new budget" and search for the budget category from the master list.
- Enter the amount to transfer and a note as to why the transfer is needed.
- As long as you are not moving money into/out of the following budget categories, no further approval is needed:
4* - Any budget category with the FURNITURE & EQUIPMENT heading
9A - FUNDED - UNALLOCATED
9B - PENDING BUDGET APPROVAL
9C - PENDING FUNDING APPROVAL
If you have submitted a budget transfer and it is listed as Open/Pending, you MUST update it to "Proceed" in order to send Construction Accounting an email to approve your budget transfer.