ACC User Guides
ACC Learning Center Links
Getting Started in Cost Management (25 minutes)https://learnacc.autodesk.com/build-getting-starte...
Correspondence
Correspondence
Utilization of the Correspondence Module: Locate your project in the ACC Project Finder- To...
Documenting Existing Correspondence
Using the Correspondence Module in Autodesk Construction Cloud (ACC) Step 1: Locate Your Project...
Generating New Correspondence
Creating and Managing Project Communications in ACC Use the Correspondence tool to make project ...
Managing Correspondence Notifications
When correspondence upload or import succeeds or fails, email notifications are sent to the affec...
RFI's
Submittals
This chapter is regarding how to submit, review, and respond to submittals.
Creating Submittal Items
Using the Submittals Module in Autodesk Construction Cloud (ACC) Roles: UF PD&C Project Manage...
Processing Submittal Items
Overview of how to process submittal items within the Submittals tool after creation. Key Topi...
Submittal Packages
How to create and manage custom packages to group related submittals. What Are Submittal P...
Cost Management - General
Cost Management - Budget
Create Planning Budget - Project Manager
Set Up an Initial Program Budget for an Unapproved/Unfunded Project Click Edit mode. Clic...
Fund a Budget - Cost Manager
This step should only be done by a Cost Manager after the Tracker Funding Request has been filled...
Create Internal Budget Transfer - Project Manager
To create an internal budget transfer, complete the following steps: Click Edit mode from the ...
Approve Internal Budget Transfer - Cost Managers
When a Project Manager creates an internal budget transfer, it must be approved. Change the vie...
Cost Management - Cost
User guides pertaining to contracts, purchase orders, pay applications, invoices, and expenses ar...
Create an Unencumbered Expense
Unencumbered expenses should be entered into ACC Cost as an "Expense". From the Cost page, cli...
Create a Purchase Order
Click the Edit mode button on the Contract tab. Click the blue + Add button to add a new "cont...
Create a Contract
Click the Edit mode button on the Contract tab. Click the blue + Add button to add a new "cont...
Cost Management - Change Orders
Meetings
This page contains information about the "Meetings" module in the ACC Build tool.